Solutions · Power Infrastructure

On-site power generation for data centers

PacinfraX energizes AI data centers with on-site natural gas generation, battery storage and a bridge to the grid. Your halls run on power built next to them, so capacity does not depend on the interconnection queue, and the utility connection follows when it is ready.

Updated

  • 1,200MW

    Planned in Vietnam

  • 4

    Site agreements in Vietnam

  • 10–50MW

    Hyperscale block size

  • 3

    Markets: Texas, Minnesota, Vietnam

Who it's for

Who needs on-site power

Any AI deployment that cannot wait years for a grid connection benefits from power built on the campus. On-site generation gives you a date set by the campus schedule, not the utility's and a supply that the campus team operates for you.

  • Hyperscalers and AI labs

    Training campuses where the date power arrives sets the date the cluster starts.

  • Neoclouds and GPU providers

    New capacity that has to be sold before demand moves on.

  • Enterprises

    Dedicated AI capacity with firm, on-site power.

Need the power and the building? See AI data centers.

The problem

Why the interconnection queue sets the schedule

A grid interconnection request passes through studies, upgrades and construction by the utility. The sequence belongs to the utility, so your date depends on its work. On-site power changes who controls the sequence: generation, storage and halls are built on one site by one team.

How the two paths compare

The diagram compares the two paths. On the queue path the data hall waits for the grid. On the on-site path the hall energizes from local generation, and the grid arrives later as a second source.

Diagram: queue vs on-site power
Diagram: interconnection queue path compared with energizing on site
Interconnection queue path compared with energizing on site.

The model

Three layers: generation, storage and the grid bridge

Our power model has three layers that work together. Generation supplies the energy. Storage handles the fast changes. The grid connection arrives as a bridge and later as a second source.

  • On-site generation

    Natural gas reciprocating engines or turbines supply continuous power to the campus.

  • Battery storage

    Batteries give ride-through, peak support and smoothing of fast AI load swings.

  • Bridge to grid

    The utility interconnection is added later and joins the same switchgear.

Diagram: power-first model
Diagram: on-site generation and battery storage feed switchgear and data halls, with the grid as a later bridge
On-site generation and battery storage feed switchgear and data halls, with the grid as a later bridge.

How we deliver

From load definition to bridge in six steps

Generation

Natural gas generation next to the halls

Natural gas engines and turbines are mature, widely supported machines with established fuel supply, maintenance and permitting practice. We select the prime mover for the campus: fast-start reciprocating engines suit modular growth, while turbines suit larger blocks.

Redundant units and servicing

Generation is arranged in redundant units, so one machine can be serviced while the others carry the load. Heat from the plant is a design input for the campus, and the switchgear sits between the plant and the halls.

Photo: Gas engines hall
Hall of natural gas reciprocating engines with exhaust stacks

Storage

Batteries for ride-through and fast load changes

AI training loads swing quickly as thousands of GPUs start and stop together. Battery storage absorbs those swings, carries the halls through short disturbances and lets the generators run smoothly. Storage also supports peak demand, so the plant is sized for steady load rather than every spike.

Photo: Battery storage containers
Row of battery energy storage containers beside a substation

Design basis

Design basis for campus power

Campus power design values
Design basis for campus power
ElementDesign intent
Prime moversNatural gas reciprocating engines or turbines in redundant units, sized to the campus block plan.
FuelPipeline gas supply with metering and a valve station at the campus boundary.
StorageBattery energy storage for ride-through, peak support and smoothing.
SwitchgearMedium-voltage switchgear with transfer between generation, storage and the grid.
RedundancyN+X set per hall and agreed at basis of design.
ControlsCampus control room with single-line diagrams, alarms and dispatch of generation and storage.
GridInterconnection added as a bridge that joins the same switchgear.
Photo: Gas valve station
Natural gas valve station and metering skid outside a plant

Bridge to grid

The grid arrives later and changes nothing for you

The interconnection path continues in parallel. When the utility connection is ready, it joins the switchgear as another source. Your halls keep the same supply, and the campus gains a second path for resilience and for balancing cost.

Read the detail on bridge to grid.

Diagram: on-site power first
Diagram: energize on on-site power first, add grid interconnection later
Energize on on-site power first, add grid interconnection later.

Operations

One control room for the power plant

Operators watch generation, storage and switchgear from one control room. Single-line diagrams show every source and breaker, and alarms route to the right team. You see the same signals for your halls.

Photo: Operator control desk
Operator desk with power control screens and single-line diagrams

Permitting and safety

Permits, emissions and safety are part of the plan

A power plant on a data center campus needs air permits, construction permits and a fuel supply agreement. We start that work with site selection, because the permitting path shapes where the plant sits and how it is arranged. Emission controls, stack design and monitoring follow the rules that apply to the site.

Safety design for gas equipment

Safety is designed in, too. Gas equipment sits in its own zone with detection and shutdown, batteries sit in separated enclosures with monitoring, and the control room can isolate each source independently.

Permitting and safety measures
  • Air permitting prepared with the site and plant layout.
  • Gas detection, venting and emergency shutdown for the plant zone.
  • Separation distances and fire protection for battery enclosures.
  • Noise and exhaust design for neighbors and the campus itself.
Photo: Engineer at a substation
Field engineer with a laptop beside a substation fence

Where available

On-site power where we build

On-site power is planned into each campus from the first drawing.

Where we build: Texas, Minnesota, Vietnam
Data center campus site in South ERCOT, Texas

South ERCOT, Texas

An AI campus in development with on-site gas generation and storage, planned so halls energize without waiting on the interconnection queue.

Explore the Texas campus →
Data center campus site in Vietnam

Vietnam

1,200 MW planned across four sites. Nam Thang Binh, Da Nang leads with 200 MW and a 20 MW phase 1 targeted for 2026–2027.

Explore Vietnam sites →

FAQ

On-site power generation questions

What is on-site power generation for a data center?

It is a power plant built beside the data halls, so the campus runs on its own supply instead of waiting for a grid connection.

Why does on-site power speed up energization?

The interconnection queue sets the utility's schedule. On-site generation puts the schedule in the hands of the campus team, so halls energize when the plant and halls are commissioned.

What fuel do you use?

Natural gas, delivered by pipeline to the campus. Engines and turbines are proven machines with established supply and service.

What does battery storage do for AI loads?

It provides ride-through, supports peak demand and smooths the fast swings of GPU workloads so the generators can run steadily.

4 more questions
What happens when the grid connection arrives?

It joins the same switchgear as another source. Your halls see the same supply, and the campus gains a second path.

How much redundancy do I get?

Redundancy is set per hall, usually as N+X, and agreed with your engineers at basis of design.

Where is on-site power available?

South ERCOT, Texas, with on-site gas generation and storage planned for the AI campus in development; Minnesota, powered industrial site; and Vietnam.

Can I buy power without a building?

No. PacinfraX supplies power as part of data center capacity on its campuses.

Request capacity

Request powered capacity for your next AI campus

Tell us how many megawatts you need, where and when. We come back with a site, a power plan and a delivery schedule.

  • A power plan sized to your load
  • A delivery schedule for the first block
  • One team for plant and halls

Request capacity or write to [email protected].

One form, one team. Requests go through our contact page and reach the capacity team directly.

Request capacity