Locations · Texas

AI data center campus in South ERCOT, Texas

PacinfraX is developing an AI data center campus in South ERCOT, Texas, with on-site natural gas generation and battery storage designed alongside the halls. It serves hyperscalers, AI labs, neoclouds and enterprises that need energized capacity without waiting on the interconnection queue. The grid connects later as a bridge.

Page updated

Texas campus key facts

Location
South ERCOT, Texas
Status
AI campus in development
Power
On-site natural gas generation and battery storage
Offering
Build-to-suit, powered shell, AI and GPU colocation

Power path

Energize on site, bridge to the grid later

The Texas campus is built around its own power. Natural gas engines generate electricity on site, battery storage smooths the load and rides through changes, and switchgear feeds the data halls directly. Because generation sits beside the halls, your energization date follows construction, not a queue.

How the grid joins the on-site power later

Grid interconnection is added as a bridge. Once it arrives, the campus runs with both sources, which gives you resilience that a single feed cannot. The design team sizes generation, storage and switchgear together with each hall block, so a new block adds power in step with load. Read the full model on data center power infrastructure, or compare the same approach at our other locations.

Diagram: Texas campus layout
Diagram: Texas campus with on-site gas generation, storage and data halls
Campus layout: gas generation and storage feed switchgear, which feeds the halls.
Flat South Texas ranchland at dawn with transmission lines on the horizon

Why South ERCOT region

Flat land, gas supply and room to phase

We plan the Texas campus around open, level land for large halls and a power island, with on-site generation designed beside the halls.

Room to phase and on-site generation
  • Room to phase. Halls are added block by block without moving the power plant.
  • On-site generation. Natural gas engines and storage sit beside the halls and are designed with them.
  • Delivery planning. We plan equipment logistics for switchgear, engines and cooling plant early in the design.

What you can build here

Four ways to take capacity in Texas

Pick the model that matches how much of the build you want to own. The reference hall is the same in every model.

Photo: gas engine hall
Hall of natural gas reciprocating engines with exhaust stacks
  • Build-to-suit halls

    We design a hall to your rack density, cooling method and fit-out schedule, then build it on the campus power island.

  • Powered shell

    You receive an energized building with power, cooling plant and fibre entries, and you fit out the white space with your own team.

  • AI and GPU colocation

    Liquid-cooling-ready halls let you place GPU clusters by the row or the hall without building anything yourself.

  • Phased growth

    Start with the hall you need and add blocks on the same site as your load grows, with one design review for every phase.

Compare the models in detail on AI data centers or start with racks on AI colocation.

Natural gas turbine generators beside a data center power yard

Design standard

What every Texas hall is designed around

Each hall is drawn as one system: power, cooling, network and security are designed together, so your engineers review one package instead of four.

Redundant power and liquid cooling
  • Redundant power. Separate A and B feeds run from switchgear and UPS to every rack row.
  • Liquid cooling ready. Coolant distribution, manifold space and floor loading are planned for dense GPU racks.
  • Carrier-neutral network. A meet-me room and diverse fibre entries give carriers a clean path in.
  • Layered security. Perimeter, building, hall and rack controls are specified in the design package.

See how colocation customers move in on the AI colocation page, and how hall blocks scale on AI data centers.

Choosing a path

Grid queue or on-site power: how the options compare

Large loads in Texas plan their grid relationship deliberately. ERCOT states that it manages power flow to more than 27 million Texas customers, about 90 percent of the state’s electric load, and a new multi-megawatt load enters a busy system.

Diagram: grid queue vs on site
Diagram: interconnection queue path compared with energizing on site
The on-site path starts delivering power while the grid connection is still in progress.
Waiting for the grid and energizing on site compared
Comparison of power paths for a Texas data center
PathHow it worksBest for
Wait for a grid connectionEnergization follows the interconnection queue and utility upgrades.Operators who can stage deployment years out.
Energize on site, then bridge to gridOn-site generation and storage carry the load first; grid connects later as a bridge.Buyers who need compute online on a defined schedule.
Natural gas infrastructure on open plains under a wide evening sky

Workforce and logistics

How we plan the team and the logistics

Building and running a campus takes electricians, mechanical and controls technicians, civil crews and operators. We recruit locally in Texas first, and open roles are listed under careers.

We plan the delivery of switchgear, engines and cooling plant with the construction schedule, so equipment arrives when the halls are ready for it. Public agencies and community groups can reach our team on the government and community page.

How we deliver

From requirement call to energized hall

  1. Current step

    Requirement call

    You share load, timeline, cooling method and fit-out model. We reply within two business days.

How to engage

What to bring to the first call

Load, timeline, model and cooling
  • Load. Total megawatts and the size of the first phase.
  • Timeline. The date racks must be powered.
  • Model. Build-to-suit, powered shell or colocation.
  • Cooling. Air, rear-door or direct liquid cooling.
If you do not have every answer yet

If you do not have every answer yet, bring what you have. A first call works with a rough load range and a target quarter, and our engineers help you size the first hall, choose the cooling method and sequence later phases. After the call you receive a short written summary of the options we discussed, so your team can review them together.

Landowners, EPC firms and technology suppliers can start at partners. Read why this model works on why PacinfraX.

Graded industrial site with survey stakes and earthmoving equipment

Questions

Texas data center FAQ

Where is the PacinfraX Texas campus?

The campus is in the South ERCOT region of Texas. It is an AI campus in development with on-site natural gas generation and battery storage.

How is the Texas campus powered?

On-site natural gas generation and battery storage supply the halls. The power plant is designed together with the data halls, and a grid connection follows as a bridge-to-grid path, so you energize without waiting on the interconnection queue.

How much capacity can I reserve in Texas?

Capacity is allocated hall by hall against your requirement. Request capacity with your load, timeline and fit-out model, and our team replies within two business days with the phase and hall that fit.

Can I bring liquid-cooled GPU racks?

Yes. Halls are liquid-cooling ready, so direct-to-chip and rear-door designs can be planned from the first drawing. See the cooling options on our AI data centers page.

3 more questions
What delivery models are available in Texas?

Build-to-suit, powered shell and AI colocation. Build-to-suit and powered shell suit hyperscalers and AI labs; colocation suits teams that want racks without a construction program.

What happens after I request capacity?

We reply within two business days, hold a requirement call, run a design review with your engineers, and issue a phased proposal. Each step has a named owner on our side.

Do you offer hydrogen or ammonia at the Texas campus?

Our hydrogen and ammonia program is a development effort co-located with campus power, for industrial and marine buyers. We are seeking technology partners and offtakers.

Reserve capacity in Texas.

Tell us the load you need, your timing and your fit-out model. We reply within two business days.